Senior Civil Project Manager
Hand over live subcontractor variations, progress claim cut-offs, and site contacts before finishing on a project.
Fictional example handover
Sample names, organisations &.example emails01Who should they call first?
- Subcontractor site contact: Northside Civil Operations Lead Mark Vance (mark.vance@civilpro.example) — call directly before issuing formal variation notices.
02What is mid-flight right now?
- Stage 2 Trunk Drainage Upgrade — Variation #14 ($185k) awaits geotechnical test sign-off before the 28th claim cut-off.
03Regular meetings & key dates
- Weekly Superintendent Progress Sync: Every Tuesday 8:30am on site to clear open RFIs and provisional sum items.
04How things actually run
- Progress claim review workflow: Reconcile quantity surveyor measure in the shared project folder by the 22nd so payment schedules issue on time.
05Past decisions & watch-outs
- Commercial retention decision: Approved holding 5% bank guarantee retention until practical completion defects are signed off.
Common questions
What belongs in a construction project manager handover?
List open subcontractor variations, upcoming Security of Payment claim cut-offs, active RFIs and hold-points, primary site contacts, and recurring superintendent meetings.
How should incoming project leads handle urgent claim dates?
Put time-critical claim and certificate dates under 'What is mid-flight right now?' and 'Regular meetings & key dates' so the incoming lead or project director can check them in Week 1.
Can the handover checklist be printed for a site folder?
Yes. Anyone with the handover link can tick off items in the browser, copy the notes as Markdown, or print / save a PDF copy.